Estimate cubic yards, tons, material volume, and total cost for foundations, trenches, and excavation backfilling.
This backfill calculator estimates the total volume in cubic yards (or cubic meters) and total weight in tons needed to fill trenches, foundation walls, retaining wall cavities, and hollow excavations. Simply select your material type, input excavation dimensions, and factor in compaction and waste loss.
| Material | Drainage | Compaction Ease | Best Used For |
|---|---|---|---|
| Crushed Stone / Gravel | Excellent | Very High (Self-consolidating) | Retaining walls, French drains, utility pipes |
| Sand | Good | High (when moist) | Pipe bedding, electrical conduit backfill |
| Common Dirt / Clean Soil | Poor to Moderate | Moderate (Requires lifts) | General grading, deep non-structural filling |
Our recommendation: For structural foundations or behind retaining walls, clear angular aggregate or crushed stone provides superior drainage and long-term stability against settlement.
When soil or aggregate is excavated, it expands (loose volume). When backfilled and mechanically tamped with a plate compactor or roller, it compresses (compacted volume). You must order more loose material than the geometric void space to ensure proper fill levels.
| Material State | Volume Change Factor | Compaction Allowance to Add |
|---|---|---|
| Coarse Gravel / Aggregate | Minimal shrinkage | 5% – 10% |
| Sand Fill | Slight settlement | 10% – 12% |
| Common Excavated Dirt | Moderate compaction | 15% – 20% |
| Clay Soil | High swell/shrinkage | 20% – 25% |